I am writing to inform you that this week sheeting piling activities are due to recommence at our site on Eau Brink Road.
These works will begin today and will last for 1 week. They will then recommence on the 25th May for 7 weeks.
We will be using three different installation methods: excavator, leader rig and crane with piling hammer. Following the vibration monitoring undertaken on Phase 12 of our works, neither the excavator or leader rig activities will cause any significant noise or vibration, however the crane with the piling hammer works that are due to commence on the 8th June are likely to cause some. These works will continue for three weeks and vibration monitoring will be set up again during this time.
We have posted this information on the Wiggenhall Next Door site and on our Community Notice Board. We obviously aim to cause minimum inconvenience and noise.
Nicky Paine
Liaison Manager | Balfour Beatty | UKCS | Regional South Business Unit